Contractor’s Update

The refurbishment works to the existing building have been completed including new ceiling and lighting, new flooring, redecoration and installation/refurbishment of the toilets, ready for when the school returns on Monday following their Easter break.

The new extension:  The windows have been installed and the roof tiling reinstated, along with the internal walls have been plaster boarded in readiness for the plastering next week. Externally, works have commenced on the new ramps.