Contractor’s Update

Internally – We have completed the plastering and the ceiling has been fitted, the mechanical 2nd fix and Carpentry 2nd fix.

Externally – The brickwork to the ramp area has been completed, and the steps and path at the rear of the building have been formed.

Moving on next week, internally, the decorators will be starting, along with the electrical 2nd fix and the flooring is be installed.

Externally, we will be tarmacking and installing the canopy.

Contractor’s Update

The refurbishment works to the existing building have been completed including new ceiling and lighting, new flooring, redecoration and installation/refurbishment of the toilets, ready for when the school returns on Monday following their Easter break.

The new extension:  The windows have been installed and the roof tiling reinstated, along with the internal walls have been plaster boarded in readiness for the plastering next week. Externally, works have commenced on the new ramps.

Contractor’s Update

Internally – We have completed the Mechanical & Electrical strip out works and installed the new distribution board, completed the new partitioning walls and plastered in preparation for the new extension.

Externally – We have taken out the brick columns and completed the block and beam flooring.

Please don’t forget if you have any concerns, questions, complaints or compliments, to contact us, via email grovelands@baxallconstruction.co.uk or via our Site Manager Steve Best 07843 355029

Contractor’s Update

We have completed the excavations for the foundations this week, which have now been poured,  the drainage is currently being excavated and laid, and we are looking to complete this early next week.

Moving forwards next week we will be undertaking the reduced dig to the foundations and commencing the block work.

Contractor’s Update

The haul road has now be put in place to allow for access in and out of the site, and the site set up has been completed.

Fencing has been taken down and tarmac removed of the footprint of the new building ready to start the dig out of the foundations next week.

During the works, if you have any concerns, questions or comments, please do not hesitate to contact our site manager Steve Best on 07843 355029.

Work Has Begun

Work has begun on our new extention which is due to completed by June 2018. A new road has been dug to enable the contractors to get their equipmet on site, as well as a site office. The children have been enjoying watching the diggers at work and have also been using construction materials in the nursery for role play.